Kismaayo Urban Water Supply

Kismayo Urban Water Supply & Sanitation Project

Project Overview

The Ministry of Energy & Wate Resources of Jubaland & International Organization for Migration are jointly Implementing Kismaayo Urban Water Supply & Sanitation Project in Kismaayo Supported by the Ministry of Energy & Water Resourcces of Federal Government of Somalia , the project is funded by the African Development Fund & African Development Bank. 

International Organization for Migration (IOM) is the project implementing partner, with close collaboration with Ministry of Energy and Water Resources of Jubaland State. 

 

Project Lots

 The Project infrastructure are categorized into the following lots; 

Lot 01: Yoontoy water treatment works - stilling well, chemical dosing channel & electro-magnetic, scour & overflow chambers, flocculation basins (2nr), sedimentation tanks (4nr), filters, filter gallery and filter control room, storage tank (1000m³), backwash  water tank (250m³ ), chemical storage, mixing and dosing building, chlorine storage and mixing building, pump house, air blower room, generator room, administration building, site and ancillary works at treatment works site, electro-mechanical equipment and electrical works.

Lot 02: Yoontoy Treatments Works (Backwash & Sludge Units), Yoontoy intake works, raw water pumping main (RWPM), Yoontoy water treatment works, Kismayo storage tank - 2,500m³ capacity.

Lot 03: Rising Mains and distribution Lines - treated water pumping main (TWPM), distribution main.

Project Objectives

 The overall project objectives are;

(i)to increase access to safe water 
(ii)improve sanitation 
(iii)strengthen the capacity for improved water and sanitation services delivery, 
(iv)reduce economic and social exclusion of poor and vulnerable groups of the population living Kismayo towns. 
The objectives are to be achieved through the following three project components: 

(i) Construction / rehabilitation of Water supply and sanitation infrastructure, 

(ii) Capacity development and, 

(iii) Project management.

Dart in the center of dartboard

Project Geographic Coverage

 
The Project target Geographical Area is Yoontooy village at Kismaayo Town , Lower Juba Region , Jubaland state of Somalia.

GPS Marker with Target

Project Components

1. Construction / rehabilitation of Water supply and sanitation infrastructure

2. Capacity development

3. Public hygiene awareness and training shall be undertaken as part of the interventions.

4. Construct sanitation facilities in schools, health centers, and markets.

Progress

Intake Works

The construction of intake work is ongoing
Raw Water Pumping Main (RWPM)
- Excavation of the RWPM is complete
- Laying, joining, testing and backfilling is ongoing

 

30% Completed

Treatment plant

The treatment plant is 80% complete

 

85% Completed

Treated Water Pumping Main (TWPM)

The installation of TWPM is 30% complete.

 

80% Completed

Sanitation facilities

Construct sanitation facilities in schools, health centers, and markets. 

 

Done

Trainings

Public hygiene awareness and training shall be undertaken as part of the interventions. 

 

Done

Environmental Incidents Tracking

There is inaccessibility of Schools , water sources , mosques   due to the holes dug for pipeline construction which also could pose a risk to the children living in these areas during the rainy period, 
Local Leaders are complained as they have fear of Pipelines holes in falling both children and animals.

Complaints were recorded from Bula-Haji , Bula Bartire , Istanbul, Eljale 1 , Eljale 2 and New Gobweyn residents. 

 

Reach out CRM for more Info

Distribution tank (2500m3)

The construction of distribution tanks is 95% complete. 

 

95% Completed

Distribution Water main

The installation of distribution pipeline has not yet started.

 

0% Completed

Kismaayo Water Resources Assessment

Kismaayo Water Resources Assessment Report under Kismaayo Urban Water Supply and Sanitation Project.

Provision of Consulting Services for Design, Supervision and Reporting for Kismayo Water Supply System Works at Kismayo town, Jubbaland State of Somalia
CONTRACT No: SOM/2020/28

Assessment Report

Project Stakeholders

The Project is Funded by African Development Fund & African Development Bank and is being Supported By the ministry of Energy & Water Resources of Jubaland state and implemented by the International Organization for Migration (IOM).
Logo of the African Development Bank Group with two globe designs and text in French and English.

Funded By

The Project is Funded by The African Development Bank 

Seal of the Ministry of Energy and Water Resources, Jubaland State of Somalia.

Supported By

The Project is Supported by the Ministry of Energy & Water Resources of Federal Government of Somalia and Ministry of Energy & Water Resources of Jubaland state - Somalia through Jubaland Water Agency (JUWA) 

Logo of the International Organization for Migration (IOM) and The UN Migration Agency.

Implemented By

The Project is Being Implemented by the International Organization for Migration (IOM)  with Collaboration of the Ministry of Energy & Water Resources of Jubaland